Construction Updates

Brook Forest Road construction Update 2022-09-23

For Saturday September 24th, the paving contractor will be laying the final payment layer on Concord Drive, Ivy Lane, and Hampton Drive beginning at 7:00 AM (weather permitting). Please note that this work is begging at 7:00AM to allow the contractor to complete this project as soon as possible.
 For Tuesday, September, 27th the paving contractor will be laying the final payment layer on Devonshire Lane, and westbound Mockingbird Lane at Midwest Road. (weather permitting)
 The Village’s engineer continues to work with the paving contractor on expediting the remaining work. Your patience during this challenging time is truly appreciated, and please know that Village staff is working diligently on a solution to complete the project as soon as possible.